ZRC Building Renovations


2019 Front of Sanctuary Renovation

In 2019, the front of the sanctuary underwent a major renovation. The Choir pews and piano/organ compartments were removed by ZRC volunteers before construction started. Honeybrook Construction then came in and began demo. Worship services were held as usual, but with the lectern in front of the temporary partition wall. The beautiful stained glass windows that had been hidden since the 70’s were exposed once more and the old hardwood floor was exposed and refinished.

A new piano was purchased and a new pulpit was built and installed by Horizon Kitchens.

Here is a short timelapse of the first day of demo.

Below are a few photos of the process as well as before and after photos.


2020 Fellowship Hall Renovation

In 2020, the Fellowship Hall was remodeled for the first time since 1974. The ceiling tiles were replaced with Drywall and the entrance was redesigned with a new handicap ramp and steps.

Concrete demo for handicap ramp on March 19, 2020

ZRC volunteers installing the new flooring on June 6, 2020

Below are some photos of the process.